3 ms·
There seem to be a lot of these? There are two different ones in Moss Landing, one by Tesla: > What might be a little confusing is that PG&E itself is also bui
by skybrian 6y ago
There seem to be a lot of these? There are two different ones in Moss Landing, one by Tesla:
> What might be a little confusing is that PG&E itself is also building a similarly named battery storage project in the area - called Moss Landing BESS - at the site of the utility’s Moss Landing substation. PG&E’s project, currently under construction using Tesla Energy battery storage system equipment, will also be among the world’s biggest battery storage projects when completed, at 182.5MW / 730MWh.
I guess it's a good location due to the substation, which is probably there due to the power plant.
(Also, I thought Tesla got rid of their PR department?)
- jeffbee 6y agoThere are quite a few going up right now. There is a 50MW/4-hour facility almost complete near me in Pittsburg, California. PG&E has 750MW new capacity planned through 2023, and the whole state has 2000MW planned for the next 12 months. The state wants 2000MW per year for at least the next ten years. I don't know why Moss Landing is so intense but basically any place with a peaker, an existing large-scale solar, or any kind of transmission capacity in California is getting batteries now or soon.
- nomel 6y agoI'm having trouble figuring out how the money flows around these batteries. Any insight or links that could be useful?