What works well for me: 1. Split the project into tasks. (a task taking at least 3-5 PTs) 2. Have a POC / prerelease phase 3. For complex tasks introduce a s
by fn1 6y ago
What works well for me:
1. Split the project into tasks. (a task taking at least 3-5 PTs)
2. Have a POC / prerelease phase
3. For complex tasks introduce a second polishing task, like "Basic User management 1/2" and later "Basic User management 2/2". If the second one isn't needed: Great!
4. For all tasks/areas estimate a lower and an upper estimation in hours or PT.
5. Revisit your estimation afterwards using this process:
5.1. Imagined that someones gives you the following choice:
You get 1000$ if your the true value lies within your estimation 90% of the time.
Or you can roll a dice and in 9/10 you get the 1000$.
5.2 If confidently pick your estimation ("I'm 100% sure the true value is within my bounds") then it's too wide.
5.3 If you rather pick the dice-roll, then you don't trust your estimation, it's too narrow.
5.4 Adjust your estimation until both options seem equally probable to you: dice-roll or your estimate being true 90% of the time.