I feel like I can get pretty good estimates on the following conditions: - the application is thoroughly specced. You might need WEEKS for this. - all variable
by tobyhinloopen 6y ago
I feel like I can get pretty good estimates on the following conditions:
- the application is thoroughly specced. You might need WEEKS for this.
- all variables are taken care of. Stack is known, and you’ve experience with all parts involved. If you don’t, get familiar with the parts first. Again, might take weeks.
- there is no implicit functionality. It is either explicit or not included.
- there are clear boundaries and rules to prevent feature creep.
- you cannot estimate an estimate
- all designs and UX are final
Now the problem is, this estimate is really expensive, because it’s actual work. It takes about 10-25% of the total project time to estimate the project.
- commandlinefan 6y ago> the application is thoroughly specced. You might need WEEKS for this More weeks than it will end up taking to build the finished product, in fact.