That’s the ampacity of wire, field-installed in conduit, per the NEC. This isn’t directly relevant to things in cars. Here’s a table that may be more relevant
by amluto 6y ago
That’s the ampacity of wire, field-installed in conduit, per the NEC. This isn’t directly relevant to things in cars. Here’s a table that may be more relevant:
http://www.ecswire.com/mmspecs/Specsheets/Belden/leadWireSelectionChart.pdf http://www.ecswire.com/mmspecs/Specsheets/Belden/leadWireSel...
So you don’t actually need so big a cable. You also wouldn’t normally be using MV cables for a car charger — getting 15kV safely through a car charger terminal sounds like an interesting challenge. But 450A at 1kV doesn’t sound like a particularly big deal.
Keep in mind that there’s potentially a free factor or 2 available. I don’t know how actual DC chargers work, but I imagine you could supply -1kV and 1kV relative to ground without too much trouble, resulting in effectively 2kV while only operating at 1kV relative to ground. AIUI you trigger rather more onerous NEC rules if you get to much higher voltages relative to ground.
- octoberfranklin 6y agoThe NEC is basically the fire code for building wiring. It's not a general safety code. It's 80% about making sure buildings don't burn down, and 20% about peoples expectations about what parts of their house can shock them if a fork is stuck into them. That's it.
- amluto 6y agoIf you look at the actual construction of a Supercharger station [0], the charger stall units don’t have any power electronics. There is a pair of big DC wires from each stall unit running to the big AC-DC units that are usually behind a fence. Regardless of how anyone may feel about the NEC, this is a field installation that needs to follow the rules. So those big cables will be sized per the NEC ampacity tables, and they will follow NEC rules based on their operating voltage. [0] I randomly stumbled on one under construction.