First, the best ever PM book I have read is "How to cheat at IT project management" Second, you can set your users up in a global resources file and track thei
by phlux 15y ago
First, the best ever PM book I have read is "How to cheat at IT project management"
Second, you can set your users up in a global resources file and track their availability across multiple project.
You could also get your hands on CBT Nuggets training - which is great.
You should require your company to fund some training for you to succeed in this position - CBT Nuggets training DVDs, Lynda.com account etc... are very affordable - especially when you are tasked with tracking 45 people - that is a hell of a lot of people to track if you are brand new to it.
To answer your question, you can click on RESOURCE tab, then NEXT OVER ALLOCATION to have project check for over allocations to your staff (RESOURCES)
Also, click on VIEW, then on RESOURCE USAGE to show the allocations of the resources. It will give a summary as well as a detail of the items they are assigned to.
Obviously, this is all predicated on accurate assumptions on your part as to how long something takes.
What you may find easier at first, is to allocate resources to tasks at a higher level in order to build out the project, for example, you may want to assign the "IT TEAM" "Setup Server Environment" as a multi day task, say 1W -- then assign "DEVELOPMENT TEAM" a multi day task, "SETUP DEV ENVIRON"
Then underneath these, break out the subtasks "SETUP WEB SERVER, 1-day" "SETUP DB SERVER 1 day" etc...
Work your way through the tasks refining the time allocation each iteration, based on input from the team.
You should save out these setup processes out to re-use them as you move forward.
When you get status from a team member on the completion of an item, ask them how long it actually took.
If they have 2 days allotted to setup a server, but they wait till the end of the second day and the setup only takes 2 hours... you need to find that out, and document it.
Ultimately, this will build an understanding of actual time costs for actions and you'll be able to build out skeletal plans very easily and know when others are making misstatements about durations...
Hope that helps.
Watch the lynda.com ms project vids - if you're in a crunch, PM me and Ill get you them...
- _ud4a 15y agothanks for the detailed response. really appreciate it and i'm going to check out the lynda.com videos tonight when i get home. cheers