My team uses story points to estimate large projects over long periods of time. Sometimes things are overestimated, and other times things are underestimated. H
by steelframe 6y ago
My team uses story points to estimate large projects over long periods of time. Sometimes things are overestimated, and other times things are underestimated. However, when you sum them all together, the errors tend to cancel each other out.
I've found that upper management doesn't care whether any given task actually takes 3 days when we estimate it at 3 days. They just want to see a schedule where each task is estimated to take X days. It communicates that you've really thought through the plan. Then, in terms of results, what they really care about is that we track to the date we committed to for the overall effort.
If a senior director is drilling down into a schedule and asking, "Why is this 5-day task taking Bob 7 days to finish?" that's a strong signal that it's time to change your management.
- Fire-Dragon-DoL 6y agoI didn't say anything about drilling, just that you can have a minimum and maximum range. This can also give you a minimum and a maximum for when the project is done. This is actually very useful in large projects, because it lets you identify upfront what are the greatest factor of risks of a project. It didn't want to be a discussion of how management is done, just to highlight that having a time range seems to provide more information to management, which is usually what's desired.