4 ms·
Well we were starting a new clustered, virtualized hosting environment so we had hard cash needs to get our first set of servers and equipment and data center s
by ezmobius 18y ago
Well we were starting a new clustered, virtualized hosting environment so we had hard cash needs to get our first set of servers and equipment and data center space. So it's a little different then starting a software company without the same hard costs.
We basically built something like ec2 but with more advanced features like load balancing and clustered, posix compliant filesystems. And we shipped before ec2 came out or was even known about publicly. This kind of system costs $$ to do right so the 120k went mostly to hardware and data center costs to bootstrap us to the point where we could take customers.
We started planning in february of 2006 and shipped in september 2006 and it's been a wild ride since then.
ps - sure, no problem. Let me know if anyone has any other questions.
pps - yeah one of our founders started Parallax who made the BASIC stamp.
- richcollins 18y agoHow did the founders pay their personal bills before the company was profitable?
- ezmobius 18y agoWe leached off of quality humans inc, which was a rails consulting shop some of our founders ran and also used savings and personal credit to get through the first 6 months or so after we all quit our day jobs ;) But lots of the planning stages, from Feb06 to August06 happened while I still had a full time day job somewhere else.