I worked at an enterprise software company with a Scrum system that used two-week sprints. This means we would estimate all the tasks for the next two weeks in
by Periodic 15y ago
I worked at an enterprise software company with a Scrum system that used two-week sprints. This means we would estimate all the tasks for the next two weeks in a big meeting at the beginning of the sprint, then at the end of the sprint we'd have another big meeting to close out the tasks and do any analysis on met/missed targets.
Tasks tended to get separated so there wasn't too much direct collaboration between coders within a sprint, and the estimations were mostly a group effort, but the person who was getting assigned a task had final say to tweak the numbers. In this environment, it was fairly easy to see who was the more productive programmers. Some people got their tasks done quickly and could easily take parts of other features, and other people were usually late and needed others to help them finish their features. If you were a programmer there, you could easily rank the programmers based on productivity. I bet QA could do the same if they tried.
However, management focused on it being a team effort. As long as we finished everything up by the end of the week they did their best to reward everyone and fire no one.