We make basically no attempts to estimate how long a feature is going to take and then update those estimates along the way. An individual feature could take a
by BrandonM 6y ago
We make basically no attempts to estimate how long a feature is going to take and then update those estimates along the way. An individual feature could take a few days to implement or several months (years even). Periodic check-ins are completely independent of the 4-week release cycle.
Every 4 weeks, we release whatever has been merged in the last 4 weeks. One dev might have 8 independent changes in a release or 0. We typically have a handful of significant changes that land each release and a bunch of minor improvements. Still, there's not much effort to estimate when any particular feature might land.
When a large feature is getting close to completion, the dev might choose to push a little bit to hit a particular release. There's not really any external pressure to do that, though.
That's still a sprint?
- srtjstjsj 6y agoYes. A key idea of Agile (maybe Scrum specifically) thinking is that you release and retrospect/rethink often, instead of long-term working on unlaunched projects from an ancient plan. I guess if you skip the rethink part than you aren't doing sprints property. An insight of Agile is that your have to pick either a feature based release schedule or a time based release schedule, not both, which is impossible and that time-based is better.