I estimate by considering an optimistic, pessimistic and normal value for each task. I then have a spreadsheet that does a modicum of statistical analysis to gi
by Lozzer 16y ago
I estimate by considering an optimistic, pessimistic and normal value for each task. I then have a spreadsheet that does a modicum of statistical analysis to give you times against probability that the task will be finished.
Some of the benefits I find are:
1. Getting into the pessimistic mindset helps produce better estimates
2. Tasks with a large spread are things you aren't really clear about, and are an obvious target to be attempted first
3. Giving a range of values to the person asking for the estimate seems to help them remember it is an estimate.
- ctdonath 16y agoNeed to include "tasks which will take significant time but I can't tell you what they are because we won't know until we get there". Managers can't seem to deal with the notion that 10-30% of a project is completely unknown when writing initial schedules.