TBH, apart from the bribes it mostly sounds pretty similar to the UK. Perhaps this person would have had an easier time if they had hired a professional to deal
by willyt 6y ago
TBH, apart from the bribes it mostly sounds pretty similar to the UK. Perhaps this person would have had an easier time if they had hired a professional to deal with it for them.
I often visit sites with potential clients and I have to tell them sorry, I can try, but you will pay a lot of fees to me and the local government and you will likely never get permission to build here.
Off the top of my head, here are some permissions / consultations you could need to build a private house in a UK, most sites wont require all of these at the same time but many sites will have a least one need for a specialist site survey of some kind:
Planning permission (Regulation of the impact of your build on the community):
- Roads department consultation
- Water supplier consultation
- Wastewater consultation with water authority and EPA
- Archaeological service consultation
- Natural heritage / ecology.
- Historic environment consultation.
- Coal authority (abandoned mines)
- Contaminated land check
- Landscape capacity study
- Full set of plans, sections and elevations and report to show:
- Materials
- Relation to existing buildings
- Effect on landscape
- Land use
- Room use
- Placement of windows / doors in relation to existing buildings
- etc...
Building control / Building warrant (Safety of the finished building):
- Radon assessment
- Structural engineers certificate.
- SAP (energy use) calculation
- Full set of plans, sections and elevations showing compliance with all building regulations
- Consultation with Fire Authority
- etc...
CDM regulations require the client to appoint a competent builder / architect / engineer etc
Party wall agreement
....and some more I can't be bothered to type out here....
This whole process typically takes a minimum of 6 months before you get permission to break ground. Some of the consultations are a one line response saying 'no objection' or they can require you to get specialist surveys done, this can drag things out longer.
For a factory the process will have several more levels of detail for each of the points above. E.g each point under planning permission might require a specialist consultant to visit the site, make tests or surveys and perform desk studies and then the submission of, I don't know, say, a 20 page written report with their findings.
- rohan_shah 6y agoWow! That's a lot of stuff. And I agree that these things need to be done. And I am not against it if the people there follow the procedure and do the things that are needed to be done. But what if one of the people from the government doing the survey/inspection just refuses to sign the paper! It's just crap. You can't complain to anyone nor can you do anything else. You're just stuck. That's where my problem lies.
- willyt 6y agoThere’s various rights of appeal, they are very slow. Also any government decision can be challenged by a judicial review in the U.K although it would be very expensive and would take years. In India, if no-one signs the paper, can you take it to court? I suppose that would take a long time too?