Omitted in the article: the reason why a gas plant (and not coal as written in the article) is picking up the load is because the french nuclear industry is yea
by guerby 6y ago
Omitted in the article: the reason why a gas plant (and not coal as written in the article) is picking up the load is because the french nuclear industry is years behind schedule for putting online the Flamanville EPR.
The original political deal was putting online the EPR then closing Fessenheim, partly to avoid going over the legal limit for nuclear power capacity set by "PPE" law in France.
According to wikipedia [1] Flamanville EPR construction started in 2007 with budget of 3.3 billions EUR and completion date of 2012.
Current estimates are 19.1 billions EUR and end of 2022 for completion.
[1] https://en.wikipedia.org/wiki/Flamanville_Nuclear_Power_Plant https://en.wikipedia.org/wiki/Flamanville_Nuclear_Power_Plan...
- dkural 6y agoAll the more reason not to close a perfectly fine nuclear plant.