I've read about a couple of solar projects that projected x/kWh and turned out to be much worse in production. Pakistan's big deployment is one example, it was
by dmix 6y ago
I've read about a couple of solar projects that projected x/kWh and turned out to be much worse in production.
Pakistan's big deployment is one example, it was planned to be 100MW but only produced 18MW. Mostly because they didn't factor in the dust that would cover the panels, keeping them clean was very expensive (I'm curious how this applies to other proposed desert deployments). Nor factoring in the typical malaise of public projects adding significant delays/costs, which is hardly unique to Pakistan when it comes to major infrastructure in 2020.
https://en.wikipedia.org/wiki/Quaid-e-Azam_Solar_Park https://en.wikipedia.org/wiki/Quaid-e-Azam_Solar_Park
Then there's the famous Solyandra which got half a billion in US tax payer money and flopped without ever being competitive price-wise: https://en.wikipedia.org/wiki/Solyndra https://en.wikipedia.org/wiki/Solyndra
Tesla's famous Australian battery factory only has enough to power 30k homes for about 1-2hrs each day. It was on-schedule, which is rare, and also makes money but scaling it up to millions of homes to make a real dent in coal would be much more challenging, especially sourcing enough lithium.
I think it's safe to take any cheery prediction from green projects and add 1.5x time/production costs and/or minus 30% of the expected output.
Note: I'm not trying to rain on the parade, I'm otherwise all for this stuff as long as it's realistic on a large scale.
- newacct583 6y agoSolyndra's failure had nothing to do with technology at all. They failed because Chinese manufacturers undercut them in price, quite severely. Allegations of dumping (or fraud, on the other side) notwithstanding, what this says is that solar is actually much cheaper and more readily available than Solyndra's investors expected. And that's sort of the opposite of your point, no? Similarly the Tesla plant is doing exactly what it said it was going to do, when it was supposed to be finished, within the budget it had, and AFAIK is making money. You're asserting that it can't scale because it... worked?! As far as the Pakistani misdesign, yeah, I'm sure that's going to happen too. Nothing works perfectly. Nonetheless this seems like a pretty oddly constructed list of reasons why solar is "much worse in production". It seems to my eyes like it's doing much better than expected.
- walrus01 6y agoI don't disagree on the point that they were undercut in price. But they were also undercut in price because commodity normal PV panels composed of 156mm polycrystalline or monocrystalline cells (60 or 72 cells) are much cheaper to manufacture than the weird proprietary system they developed. They are also much cheaper to mount on large roofs (home depot/walmart warehouse sized) or on large scale 300kW+ ground arrays. Ordinary 60 or 72-cell panels are DEAD SIMPLE in their construction. It's a sandwich of a backing material, encapsulation for the cells and soldering, glass in front, with an aluminum frame and a junction box on the rear. Solyndra "panels" are fragile, hard to transport, hard to mount, everything about them was a pain in the ass.
- nappy 6y agoYou can't fund potentially breakthrough innovation and research and only get one tail of the distribution. It's a good thing, not a bad one, the the US government providers funding, and in this case, interest free loans for projects that sometimes fail.
- jaggederest 6y agoAs I always say in software projects, if some of your tasks aren't failing, you're not being ambitious enough in your goals, or are not ditching ineffective work soon enough.
- dgut 6y agoSolar power is alive and kicking in Spain and increasingly more cost effective (removing the need of subsidies since 2018).
- toomuchtodo 6y agoSpain just shuttered half of their coal capacity at the end of June 2020 partially due to this (also because of emissions requirements owners didn’t want to meet), and intend to shutter the rest by 2025 (additional wind power and pumped hydro for storage is coming online in that time). https://english.elpais.com/economy_and_business/2020-06-29/spain-to-close-half-its-coal-fired-power-stations.html https://english.elpais.com/economy_and_business/2020-06-29/s...
- meditative 6y agoTesla's Australian battery was not for storage, it's for power quality.
- wlesieutre 6y agoIt's for both - 70% of capacity is for grid stability and the other 30% is for storing power when it's cheap and selling it back when it's expensive.
- walrus01 6y agoI'm honestly curious what is the big challenge with keeping large arrays of ground mounted panels clean in Pakistan. The prevailing wage for unskilled labor for a 6 day a week, 45-hour work week for one laborer to clean panels is probably about $250-300 a month (USD equivalent, in rupees) in that area. That would be a good wage compared to construction work or farm work in that region. With some basic equipment like rolling carts with sprayers and squeegees on extension sticks, how many individual 72-cell sized panels (1.99 x 0.99 meter size) can one person clean in one day? Multiply by probably 4 to 6 full time staff positions.
- zamfi 6y agoQuoting the Wikipedia page cited above: > It required one litre of water to clean, each of 400,000 installed panels. A total 15 days cleaning cycle required, 124 million litres of water enough to sustain 9000 people, while rain in Cholistan desert is rare and far between. Providing such huge amount of water in desert terrain, became a challenging and daunting task for management team. Besides, the manual cleaning methods allowed setting of dust before it was re-cleaned.
- riku_iki 6y agobut maybe they can use seawater for cleaning?
- vlovich123 6y agoWould the salt be abrasive & damage the panels/coating decreasing efficiency? I would imagine another challenge is the transporation costs. The nearest fresh water source appears to be Sutlej River ~18 KM straightline. The nearest seawater source appears to be the Arabian Sea, ~800 KM straightline. The cost to a problem like this would never be labor as that can be trivially automated if it ever gets costly enough. Water is expensive at these scales. That being said, it's probable that there could be solutions here. Automated scrubber/blower might be able to get most of the efficiency back without the cost (whether integrated into the panel or a robot on a track). Could potentially use any water more judiciously too when needed (moisten a scrub rather than blasting it with water). Don't know enough about the project but I would hope the domain experts responsible for the project would have considered something I only thought about for 30 seconds & there are reasons that they don't do that.
- klipt 6y agoHow high does the dust go? Maybe they could cut down on cleaning by just building a wall around the power plant, or add some fans to keep the dust out?
- ajb 6y agoWell, supposedly the Amazon is kept fertile by dust from the Sahara, so I'd guess pretty high.
- 4043D 6y agothe point of the tesla battery in south australia wasnt to provide base load continuous power it was to provide close to instant peaking power to smooth the grid it was directly competing with natural gas peaking plants. (which it beats)
- Jedd 6y ago> Pakistan's big deployment is one example .. A valid example of what can go wrong when you pick the wrong technology, don't do small scale trials first, and rely on government oversight. (Refer the Background & Operation section of the wikipedia article -- toe-curlingly alarming, yet ultimately unsurprising.) They almost definitely should have pursued concentrated solar thermal. It partly solves the 'storage problem', provides power well into the evening, doesn't need more water than they have to clean it, and improves magnificently with high temperatures (the wikipedia article cites the problem of regular 45C days, which are above the 25C optimum temperature for PV panels). Given all this was known and understood before they broke ground, this sounds like a traditional government project problem -- susceptibility to corruption, vanity, hubris etc.
- CydeWeys 6y agoIs solar thermal still a going concern? Are new plants still being built?
- Jedd 6y agoIt seems to be in a lull, but the technology is still maturing. I suspect as the generation + storage costs continue to shift, it'll be adopted more eagerly. PVCs cost reduction has been a boon for that industry, but that tech, of course, ignores the storage problem. Reading about some of the missteps of CSP, much like the above, they seem to be share similar traits of government mishandling, bureaucracy, dodgy dealings, etc. EDIT: In any case, a naive interpretation of the Pakistan project cited -- if it truly is getting ~20% of anticipated power, cost per unit is 5x forecast, at which point a CSP would have been better value for money.
- CydeWeys 6y agoWhy wouldn't solar thermal have the exact same issue with mirrors getting dusty though? I suspect that solar thermal is in more than a lull; I suspect that it's been obsoleted by PV and we aren't going to be seeing many new installations at all.
- lappet 6y agoI am curious, how do Solar Parks in India work? The Quaid-e-Azam park is in the Thar desert and the desert extends to India as well in the state of Rajasthan. India seems to have built a solar park at Bhadla, ~300 km away from Quaid-e-Azam, in a different part of the same desert. https://en.wikipedia.org/wiki/Bhadla_Solar_Park https://en.wikipedia.org/wiki/Bhadla_Solar_Park Apparently Bhadla is the world's largest solar park. I wonder if the two countries can co-operate on this (I know relations are mostly hostile currently)
- dmix 6y agoInteresting, they seemed to be attempting to solve the cleaning problem via automation from an Israeli company: > In December 2016, Solairedirect signed an agreement with Ecoppia, a PV panel cleaning solutions developer, to provide automated cleaning solutions to the project. Due to the park's location in a desert region, it is prone to dust storms https://www.pv-tech.org/news/ecoppia-to-provide-cleaning-solution-for-indias-bhadla-solar-park https://www.pv-tech.org/news/ecoppia-to-provide-cleaning-sol... Hopefully the project eventually does reach the 2000MW scale it plans. It's not clear from the Wiki how far along it is or whether it's currently operational. It mentions opening targets for Dec 2018. Softbank is involved for 500MW which is one red flag :p
- URSpider94 6y agoTesla’s famous Australian battery farm (not factory) was designed from the start as a frequency maintenance source, not as large-scale storage. It’s designed to be able to source or sink large currents with nearly instantaneous response, which is ideal for responding to sudden rises or falls in production or demand. The farm has been successful in both significantly reducing the spot price for power, but also in making money for the operator. It’s a huge success story.
- roenxi 6y ago> It’s a huge success story. The caveat being the South Australia has a power grid that is sometimes a contender for the worst managed (and most expensive) electricity grid globally. Or at least highly challenging to get it working smoothly. So the battery is a huge success story and we'll see more like it - but the conditions where it succeeded are not necessarily where the gird wants to be.
- flgb 6y ago> worst managed (and most expensive) electricity globally That's a strong claim. Wholesale electricity prices in South Australia are currently around USD$45/MWh. My understanding is that South Australia has historically always had the highest electricity prices in Australia due to dependence on gas generation within a small market controlled by two players who took advantage of their market power, but that this is starting to reverse now due to the shift to more renewables over the last decade, and South Australia may now be on track to have the cheapest electricity in Australia.
- dlp211 6y agoSolyndra didn't lose tax payers money, it was part of a portfolio of companies that made the US government money. It was literally the US government being innovative, effective, and responsible with tax payer money. By singling out Solyndra like that and calling it a waste of tax payer money, you fundamentally make it harder for the government to continue to operate in the manner described. Breakthrough technology does not happen without failure, and focusing on the failures, instead of the successes only serves to limit our future capacity for breakthroughs.