Some outcomes will be more likely than others and you can use these numbers to come up with statements like: “41 items or more can be completed in 30 days with
by Tade0 6y ago
Some outcomes will be more likely than others and you can use these numbers to come up with statements like: “41 items or more can be completed in 30 days with a certainty of 85%”.
I did something similar recently:
I started with taking the 20 tickets we closed and plotting story points vs actual time they took. Results were as follows:
- 8s were mostly garbage, but consistently took more than one sprint.
- 1s and 2s were also garbage but always took less than a 5.
- 3s and 5s were fairly consistent, but at the same time could take up to 100% more.
Conclusion: split up all 8s if possible, treat 1s and 2s as 3s.
Second, I removed the outliers and created a distribution of point-per-sprint rates.
The result: 5.6 points per sprint with a standard deviation of 2.5 - pretty bad, but from that I could tell that our chance of delivering more than a given amount of points per person per sprint was(assuming a normal distribution):
85% for 3 points.
60% for 5 points.
17% for 8 points.
4% for 10 points.
Conclusion: per sprint we should either take one 5 point task or two 3 point tasks, but avoid 5 + 3 and never take on a 5 + 5. Also take a 3 if we didn't deliver the previous sprint.
Last point: some outliers were estimated somewhat highly (5), but took much less. One feature they had in common was the word "analysis" in the ticket title.
I guess the lesson here would be to ask: are we really planning on taking a whole sprint(two weeks) to analyse something?