It may not be obvious from media reports, but Daiichi's 1, 2, and 3 reactors were in full operation when hit by the earthquake, and all three successfully execu
by patio11 16y ago
It may not be obvious from media reports, but Daiichi's 1, 2, and 3 reactors were in full operation when hit by the earthquake, and all three successfully executed emergency shutdowns within a matter of seconds. This was the single most important thing to happen, since It reduced the heat generation virtually immediately, without which it it is highly likely that at least one would have lost containment prior to emergency measures of the last few days working. The lack of graphite may have made that survivable for Japan, but the plant itself would have been virtually impossible to recover, and continuing failures would have been very, very bad for neighboring communities. (They'll probably all get to go back a few weeks after the plant is secured.)
Some minutes after the earthquake, the tsunami physically hit Daiichi and Daini. (You haven't heard of Daini in about a week because we've reestablished control there.) It wiped out their diesel generators and external power lines, because both had tolerances in the five to six meter range for tsunamis and the actual wVe was nine to ten.
Things, incredibly, still didn't go to pot immediately. They worked on battery backup for a few hours, but couldn't get an emergency plan in operation in time without power. That's when things started to get bad, principally with overheating from waste heat causing radioactive steam/hydrogen explosions, which were the first cause of radioactivity spikes and have complicated all the disaster response since. (Though, perversely, the fact that Daiichi 3 had a steam/hydrogen explosion blow the roof off made the spent fuel pool accessible to water delivered without entering the building, without which getting a hose inside would have been a one-way trip.)