4 ms·
I think changing priorities is a risk that has to be taken into account whenever you are considering any task that will extend for a long time -- rewriting code
by gonzus 6y ago
I think changing priorities is a risk that has to be taken into account whenever you are considering any task that will extend for a long time -- rewriting code is just one example.
If you have to go on for many weeks / months on a project without the possibility of showing intermediate results, it is naive not to think that there is a high risk of the project being cancelled.
- nottsdev 6y agoI completely agree with you, it is just a complicated metric to factor in. I guess one of the frustrations was the fact that our team had been been assigned with assurance that we will not be affected by changing priorities.