The non-kanbanness of software project boards is the lack of limits or limits applied to the wrong resource. E.g. the number of items of in-progress or in-revie
by karmakaze 7y ago
The non-kanbanness of software project boards is the lack of limits or limits applied to the wrong resource. E.g. the number of items of in-progress or in-review should be limited to the number of developers who perform these actions. Setting a column limit irrespective of this doesn't make sense. Also shouldn't have N cards assigned to one person and none assigned to N-1 others. In short column/state != limited resource.