I use these techniques for day-to-day estimation in software development, usually for things like project timelines, system requirements, etc. I often run into
by cpitman 7y ago
I use these techniques for day-to-day estimation in software development, usually for things like project timelines, system requirements, etc.
I often run into developers who think "there is no way to estimate when we will be done". What I think they usually mean is that they cannot estimate a single time in which it will be done, which is completely fair. However, if they are being honest with themselves, I think they can often estimate a range of possible outcomes. Adding a new "Contact Us" form may take a few hours or a few days, but it isn't going to take 1 year.
One of my bigger successes with this kind of model was sizing the resource requirements for a brand new high-performance system that was in it's early stages of development. I created a model that started with what we knew so far from out performance testing, with uncertainty for everything, and projected forward to different confidence levels of sizing. We ended up being pretty having just a little extra, which was perfect considering the multi-month procurement process.
- refrigerator 7y agoVery cool! What tools are you using for this right now?
- cpitman 7y agoFor my more routine analysis of LOE/budget, where it is mostly a straightforward summation, I have a template spreadsheet that I just reuse. For more complex cases, I hand write the equations and error-propagation into a custom sheet. A little time intensive, but it gives me an excuse to practice multi-variable calculus.