In case anybody wants an answer to that, here's mine: Cost estimates only are valuable if a) the amount of time involved is relatively large, b) you expect to
by wpietri 7y ago
In case anybody wants an answer to that, here's mine:
Cost estimates only are valuable if a) the amount of time involved is relatively large, b) you expect to learn nothing during that time, and c) the expected-value estimates are precise enough that you can calculate a narrow ROI range.
Instead, the way I prefer to work is with continuous delivery and small units of work. If you are releasing daily or more often in a context where you can learn a lot via experiments and user tests, then estimates cease to be valuable.
Another way to look at this is in terms of push systems versus pull systems. Scrum was made for push systems, where executives push large idea lumps through a plan/design/build/release process. In that world, estimates are valuable, if only because executives like to appear in control and need signals to tell them when to yell at people.
But in a pull system, you have small, cross-functional teams observing user behavior, developing problem and solution hypotheses. There, delivery is used mainly to test hypotheses, which are then revised based on new data. In this context, batch estimates are generally wasteful because new data and new hypotheses change the basis for estimation too often. There's rarely sense in estimating a month of work when every day you're learning things that change what you'll do and how you do it.