4 ms·
Total cost means nothing. What was forecast? What was the original budget? If the original was billed at 1.3 billion NOK and we're at 2 that's still very hig
by blaser-waffle 7y ago
Total cost means nothing. What was forecast? What was the original budget?
If the original was billed at 1.3 billion NOK and we're at 2 that's still very high, but it's a different discussion from a 400K NOK estimate.
"Take whatever you think you need and double it" comes to mind.
- erikbye 7y agoOf course TCO means something. You have an expected ROI when you go into an ERP. In this specific situation TCO far exceeded possible ROI.