> ... with cost overruns common. Presumably that is going to be consistent with any large industrially planned operation though. The overruns aren't going to b
by roenxi 7y ago
> ... with cost overruns common.
Presumably that is going to be consistent with any large industrially planned operation though. The overruns aren't going to be technology-specific, they are going to be related to the tendering process.
If the planners are incentivised for accuracy there will be one, maybe two overrun projects then the assumptions get adjusted. So if it is routine that suggests that there is some sort of incentive problem.
An industry planner will have little difficulty estimating an accurate cost of the technical parts of a project. Using historic averages or model + 20% contingency usually gets most of the way there. If the estimates are consistently wrong there are political issues at play.