Wait, so if I have this correct, the airport took ~6 years to construct and 9 years and counting to correct problems with its construction? Meaning that it woul
by jcranmer 7y ago
Wait, so if I have this correct, the airport took ~6 years to construct and 9 years and counting to correct problems with its construction? Meaning that it would have been faster to tear the entire building down and rebuild it from scratch than it is taking to remedy the issues?
How does that happen‽
- detaro 7y agoMassive failures in oversight and management. Airport building/management company that makes changes to the design pretty randomly, total failure in oversight mechanisms (basically, there was no review process in place which could have caught this while it was going on), as a result a building that doesn't match the original plans, doesn't conform to regulations and where in the end the actual state of what exists wasn't even known. Brought down by failing the fire safety certifications shortly before the opening, at which point the slow "figure out what happened and who to blame" process began, and then attempts to fix it. It's a glorious mess. Even if there had been a consensus on almost-rip-and-replace immediately, it's not clear that could have been done as quickly, given the amount of preparation needed. (As an example of the kind of changes, during the building process they decided to re-assign arrivals and departures to different floors of the building. Which in an airport has fairly fundamental consequences due to security zones etc...)
- freeflight 7y agoThat's what happens when political corruption becomes a culture, while nobody wants to seriously talk about it.
- _pmf_ 7y agoPoliticians take turns taking lucrative positions within the project companies, "to help".
- usrusr 7y agoAccording to lore, it all started with the architect deciding against the tried and tested usage of little chimney-like structure on top of the terminal roofs for fire protection de-fuming, insisting instead on some novel, less visible solutions for aesthetic reasons. Those then caused all kinds of follow-up issues, eventually leading into the construction equivalent of the perpetual bugfix cycle, where every fix brings two new problems. Compounded by a colorful parade of high level "fix it guys" taking over the reins and failing in short progression, adding to the chaos.
- detaro 7y agoAs far as I remember, the estimation was that the fire system was properly designed (although more complex for the mentioned artistic reasons) and would have worked - for the building that was originally planned, which the airport company then changed massively.
- flukus 7y agoSeems like there's a lesson there about sticking to tried and proven solutions even if you come up with a better one. Or maybe it's a worse is better thing?
- deleted 7y ago[deleted]
- PavlovsCat 7y agohttps://onemileatatime.com/berlin-brandenburg-airport/ https://onemileatatime.com/berlin-brandenburg-airport/ > In 2014 it was revealed that Alfredo di Mauro, the chief planner for the airport’s fire protection system, was not a qualified engineer but an engineering draftsman. He admitted this, saying everyone thought he was a proper engineer and ‘he didn’t contradict them.’ > His mistakes have cost hundreds of millions of dollars to fix. As a tangent, not to belittle the corruption around BER, and with more tongue in cheek than snark: I wonder how many people responsible for things on this list https://hn.algolia.com/?q=breach https://hn.algolia.com/?q=breach (insofar the cause was negligence) have "software engineer" in their job title or description? If you ctrl+F "engineer" in those articles and discussions, you'll see it thrown about quite casually. If architecture was like software, buildings would regularly just collapse, and sudden death would just be an accepted risk risk of going into a building or walking past one. Some people would complain about that, but we would consider them idealists and their demands incompatible with progress and prosperity.
- willyt 7y agoEmergency smoke ventilation is a solved problem, ‘little chimneys on the roof’ are one of many different solutions; there are lots of different strategies. So that sounds like nonsense. Source, I’ve worked on mega projects like this. If it’s true that someone decided to swap departures with arrivals once the building was already on site, I would say that’s your problem right there. Whoever is responsible for that caused this mess. I would hazard a guess that the airport was originally briefed to be designed as primarily a government funded transport interchange, someone decided it should make some money to help pay for the costs and the only way to make room for the extended corridors full of shops was to turn the design concept upside down.
- pteredactyl 7y agoInept State/Corporate entities who hire based on immutable characteristics of an individual rather than their actual ability to complete given task. Corrupt State/Corporate entities who'd rather have money in their private bank than complete given task for public good.
- Haga 7y agoRunning scrum on a physical waterfall with dependencies.
- PavlovsCat 7y agoWell, it's not just years, every day of that means money that gets shifted. I couldn't find the article I read years ago about one of the companies involved, and their string of similar projects in other countries, but here's something to give you an idea how much this thing reeks: https://www.bbc.com/news/world-europe-36185194 https://www.bbc.com/news/world-europe-36185194 When I read "embarrassingly poor planning" and similar phrases in articles about it, I have to think of someone who "clumsily" spills coffee on the dress of Marilyn Monroe, for lack of a better image, and then "embarrassingly" ends up with his head planted on her chest, because he "stumbled" while "hastily trying to make up for the mistake with a handkerchief". Sure, that's one way to put it. But beyond all the plausible deniability, someone is benefitting, one way or another.
- _pmf_ 7y ago> How does that happen‽ Berlin is a massive clusterfuck of corruption.
- m_fayer 7y agoLived here 10 years, can verify. You feel it even if you're not in the know. It's like NYC in the early 80s, but now mixed with a startup scene.
- perlgeek 7y agoIn addition to the excellent replies so far, there's a compounding problem: The long delay means that new safety regulations for new buildings apply, and so they have to iterate again.
- myspy 7y agoI read that it's mainly a software problem, which would make sense why the delay is so long. Building and fixing problems with the building are done faster than fixing the software to manage that airport.
- ptaipale 7y agoNo, it's not mainly a software problem. As is common in big delays, there are multiple issues, but a fairly big contributor was political arrogance that wanted to brush away fire regulations. That didn't work.
- mariorossi666 7y ago> Meaning that it would have been faster to tear the entire building down and rebuild it from scratch than it is taking to remedy the issues? This sentence is never true. It's not true in software it's even less so in construction. The issues would have been there even if the construction was done perfectly, you always fix such massive infrastructure for their whole lifetime (it's not simply a building!) This time they fucked up and the airport didn't pass the safety checks necessary to open it, but there is constant fixing and changing and upgrading and scaling in an airport facility. Tearing down it and rebuilding it it's never an option and never a good idea, unless the structure is severely damaged or contaminated (e.g. asbestos)
- advancingu 7y agoThere is a fantastic English language podcast called "How To F#€k Up An Airport" that goes into great detail about the many failures that let to this debacle. Highly recommended. http://www.radiospaetkauf.com/ber/ http://www.radiospaetkauf.com/ber/