3 ms·
> I checked with contractors and the recommendation was "just do it and don't complain or they'll make your project a living nightmare". > So, we did. > They
by shantly 7y ago
> I checked with contractors and the recommendation was "just do it and don't complain or they'll make your project a living nightmare".
> So, we did.
> They still made the project a nightmare to complete. They added a massive chunk to the overall cost and it took six months longer than it should have taken to complete it.
I read it that the excessive grounding requirements were just the beginning of a series of silly and expensive demands, which in aggregate made the project way more expensive.
It's that or it took six extra months to install four grounding rods.
- nullc 7y ago> It's that or it took six extra months to install four grounding rods. Given some contractors I've dealt with --- I wouldn't be shocked. (or maybe I would be shocked, ... if they were allowed to do electrical work unsupervised. :) )