Very much this. I try to never give an estimate without giving 2 values. The expected effort, and the expected calendar time. Sometimes I’ll also add expected c
by milesvp 7y ago
Very much this. I try to never give an estimate without giving 2 values. The expected effort, and the expected calendar time. Sometimes I’ll also add expected complexity since that adds a lot of risk to both estimates. There are lots of things I’ve done that were quite easy, then I spend lots of time just sheparding the feature into production. Especially if you’re working with other teams, or vendors, and can expect 24hr delays for every email round trip.
In fact each department or vendor involved in a project will easily double calendar date, and often complexity as well. At a previous job we automatically increased our t-shirt size for every vendor just to keep our estimates honest. And there was only like one vendor who we would make exceptions for since they were always amazing to work with.