I agree that it _shouldn't_ take that long. This project was first started in 2011. Construction won't start until some time in 2020 (optimistically). From htt
by buss 7y ago
I agree that it _shouldn't_ take that long. This project was first started in 2011. Construction won't start until some time in 2020 (optimistically).
From https://www.sfexaminer.com/news/sf-transit-board-approves-car-free-market-street/ https://www.sfexaminer.com/news/sf-transit-board-approves-ca...:
> Better Market Street will be implemented in three phases: Market from Fifth to Eighth streets is phase 1, Market from Fifth to Second streets is phase 2, and Market from Van Ness to Octavia Boulevard will comprise phase 3.
> The second phase will also include the construction of a loop in the Financial District for the F-Market & Wharves historic streetcar...
> Phase 1 is scheduled to stretch at least until 2022, according to the project’s website. The construction of the streetcar loop is expected in 2023, and future phases of the project are dependent on identifying funding
So 1/3 of this project is projected to be finished by 2022. And the other two portions of market street don't even have funding or a timeline yet. We will be lucky if it's finished by 2026 (no delays, no recession puts funding in jeopardy, etc).
By the time everything is done, it may be _20_ _years_ to build protected lanes. In the meantime, we have sharrows and intermix with taxis.