The numbers you've quoted, from page 7, are per MW mile, not per mile.
by Pinckney 7y ago
The numbers you've quoted, from page 7, are per MW mile, not per mile.
- dredmorbius 7y agoThanks, that was a really quick check. And yeah, that would increase the costs markedly. (My initial thought on posting was that $30 billion would not be enough, though the first read of actual per-mile costs, neglecting per MW-mile, seemed to suggest otherwise.)
- deleted 7y ago[deleted]
- tamaharbor 7y agoYou are multiplying transmission line costs by distribution costs per mile?
- Pinckney 7y agoThis PDF from Wisconsin puts the cost at $280k-390k/mi depending on the voltage of the line. They put the cost of underground transmission lines at $1.5M-2M/mi for the same voltages. https://psc.wi.gov/Documents/Brochures/Under%20Ground%20Transmission.pdf https://psc.wi.gov/Documents/Brochures/Under%20Ground%20Tran...