I had a similar situation in the early 2000's at NTT/Verio in Sterling, VA. They lost power because someone dug through a utility line and introduced a ground a
by jgalentine007 7y ago
I had a similar situation in the early 2000's at NTT/Verio in Sterling, VA. They lost power because someone dug through a utility line and introduced a ground a fault into their system. They switched to generators and then against protocol (basically human error) tried to force override a transfer switch onto their other utility which ended up killing the generators. Eventually the UPSs were all drained, but we had to shutdown servers long ahead of that because with no AC, they were overheating. People were taking servers out by pickup truck to stand them up at their other offices and data centers. 48 hours of pain.
- macintux 7y agoPower seems like the big wildcard in data center management. So tough to properly test your failover preparations, and so many different ways things can go wrong. I know of a large company that had the data center emergency cutoff button next to the automatic doors on the way out. Sure enough, a contractor hit it one day thinking it was the way to open the doors.