So... the reason why Pivotal Tracker is still my favorite tool is because most PM's want to know when a feature is going to be done. With PT, developers assign
by latchkey 7y ago
So... the reason why Pivotal Tracker is still my favorite tool is because most PM's want to know when a feature is going to be done. With PT, developers assign points to stories and the 3 week average (customizable) is what makes a velocity.
If velocity is 20, then 20 points worth of stories fit into an iteration (week). Points include testing, so that isn't cut out, like with sprints. As a PM, I can get developers to point stories out for a few weeks worth of iterations. If I need to move stories around, I can do that easily and I can see how moving things around affects 'when it will be available'.
If I was going to use another tool, I'd want PT's 'velocity' as a base feature for sure.
- cj 7y agoI don't think tools like this are meant to replace Pivotal (or Jira, or whatever you use for tracking Sprint stories/tickets). Roadmapping (or in this case, user story mapping) is usually done independently from Sprint planning as a way to develop and share the product roadmap so that your team can prioritize Jira/Pivotal tickets or whatever your team uses for tracking Sprint tasks.
- latchkey 7y agoYes, Pivotal model (disclosure, I worked at Pivotal/CloudFoundry for a bit) just uses sticky notes and they do this in an 'inception'. https://content.pivotal.io/blog/inception-knowing-what-to-build-and-where-you-should-start https://content.pivotal.io/blog/inception-knowing-what-to-bu... Sticky notes are something more dynamic and hand writing things out makes you think more about things than just filling out boxes on a screen. It also allow you to iterate quickly and just toss the ideas you don't like into a corner. Those stickies turn into 8 point (or unpointed) stories, put into Tracker, which then get broken down into smaller stories which can be discussed (iteration planning meetings) tasked out and worked on. So yea... I guess if someone made me use a tool like this over simple sticky notes, I'd probably be really frustrated at the end of the day.
- Redsquare 7y ago"If velocity is 20, then 20 points worth of stories fit into an iteration" -> When was software engineering so regimented, predictable and precise. This sort of mentality treats engineers as robotic and is a cancer in the industry currently.
- latchkey 7y agoActually, no. It is far less robotic in practice and works quite well because once the schedule is better known and controlled, developers can go home on time every day. The whole crunch mode thing is effectively eliminated. Pivots get into work at the same time, work together all day and then get to leave at the exact sane normal 8 hour work day. Every single day. Sounds like a great job to me.
- Redsquare 7y ago20 'points' (whatever they are) last week has zero bearing on what will be accomplished this week, or next or in 6 months time. Vanity metrics. Your silently forcing them to be a feature factory and act in a consistent robotic fashion no matter what the problem at hand is. I bet your tech debt velocity is increasing weekly.
- trastentrasten 7y agoI tend to agree. I have found the number of stories to have som utility as a metric, though.
- latchkey 7y agoThis is why velocity is a 3 week average of points and can be overridden in the tool to show people who are out on vacation/sick. The tool dynamically updates to show what stories make it into an iteration as well. The whole idea is not to force people into a box. It is to just give PM's a way to plan the future. Obviously, things can change so it isn't some forceful thing at all. Don't knock it until you've tried it. I had an opinion like you and then I went and worked in this system and it totally changed my mind.