This is one of the reasons why in the UK, back in the early 1990s, it was recommended that construction projects (both public and private) switch to what is now
by throw0101a 7y ago
This is one of the reasons why in the UK, back in the early 1990s, it was recommended that construction projects (both public and private) switch to what is now called "NEC" contracts:
* https://www.designingbuildings.co.uk/wiki/NEC3 https://www.designingbuildings.co.uk/wiki/NEC3
Most contracts are cookie cutter templates, so everyone is familiar with them and lawyers don't need to be called in to create bespoke solutions for every project. There are various options if fixed-priced or cost-plus is desired, and pre-agreed schedule is decided on so that payments only go out at specific milestones.
Can anyone from the UK comment on the pros/cons of the system?
- bmsleight_ 7y agoNEC contracts are wonderful. I say this having worked on both the client and the contractor side. Solves many, many problems and gets people working in collaboration. As a contractor I need to know the clients goals and as a client I need to help make the contract profitable. All pros - no cons from me.