That's one of the big reasons that I've become a proponent of Donald G. Reinertsen's approach to product development. He emphasizes a variation of the cost ben
by brightball 7y ago
That's one of the big reasons that I've become a proponent of Donald G. Reinertsen's approach to product development.
He emphasizes a variation of the cost benefit formula + urgency, called Cost of Delay for prioritizing that basically boils down to "Value / Time Remaining" because your cost is the time remaining. It naturally prioritizes work based on shortest time to value because, unless the value proposition is enormous, dividing by estimated time is almost always going to favor the shorter tasks.
This will of course vary by team, but in general it puts a focus on responsiveness and getting the little stuff out of the way first (including tech debt). When you have a formula that doesn't let the little stuff build up, it gets easier to focus on the big stuff too. It's also make it easy to pivot because it totally disregards prior time investments.
It meshes better with what agile is supposed to be better than any other methodology that I've encountered to this point.
- reallydude 7y ago> including tech debt Tech Debt is not little, or we wouldn't carry it around, rather than devote time (and risk of revealing new unknowns) to fixing it. My agile experience has always favored conquering little stuff first, since ppl recognize stories more than points (which vary in value, over time). This, unfortunately, sometimes leads to the hilariously subversive act of splitting a story up into as many tiny pieces as possible so that some people may inflate that "What have you done for me lately" list while more tangible coding is done by others.
- brightball 7y agoCost of Delay metrics do a good job of explaining how the cost of that debt can grow over time the longer it goes unfixed. Some are smaller than others, but uniformly it tends to get harder to fix the longer you wait to fix it. He also doesn't place any type of value in points or other, bluntly, useless metrics for measurement. The entire focus is around delivered value. You can break it into however many stories you want, the value is the same. The measurement of how many things you delivered or how much time they took is not important to the company. What's important is how much value was been delivered to the company. It's the only metric that matters.
- nitrogen 7y agosplitting a story up into as many tiny pieces as possible Honestly I think that's the intended outcome from the business's perspective. The smaller the piece of work, the easier it is to assign a cost and a benefit to it, and the easier it is to hand off to another developer.
- Groxx 7y ago>... and the easier it is to hand off to another developer. I have never seen this work out in practice. And it's like a 1%-of-the-time thing anyway. On the flipside, I've seen quite a few hours wasted adding fake subdivisions to tasks, probably close to 30% of the time. Outside of small, known bug fixes or tech debt cleanup, it's rare for a thing to wholly fit within a sprint.