> I work on one of the densest power grids in the world (NYC) on the team which does emergency transformer replacements and can possibly answer questions about
by vageli 7y ago
> I work on one of the densest power grids in the world (NYC) on the team which does emergency transformer replacements and can possibly answer questions about this. From failure to in service for a single transformer in Manhattan is down to 2-3 weeks. That includes design and engineering (my part), permitting, and construction.
Interesting. I had always wondered how utilities interact with local permitting. I had assumed they would work something out to have standardized permits for common work which they could leverage during incidents but that seems that's not the case.