> Or tasks that used to take 2 or 3 days now gets split across 2 or 3 sprints, because guy 1 can't allocate it to guy 2 until he finishes it. And it just sits a
by sethammons 8y ago
> Or tasks that used to take 2 or 3 days now gets split across 2 or 3 sprints, because guy 1 can't allocate it to guy 2 until he finishes it. And it just sits around until the next sprint.
This so much. Because no PMs want to adhere to "sprint forecast," but insist on "sprint commitments," you literally cannot commit to doing a unit of work that depends on someone else getting theirs done first until they are done. A smooth flow that gets to market quicker now _must_ be lock step gated by sprint start dates. /me sighs
- iovrthoughtthis 8y agoI imagine stuff like this is why kanban was developed.
- sethammons 8y agoI think kanban was primarily for interrupt driven projects, but this works too for pipeline like stuff.