> Everything gets a T-shirt size. Roughly, "small" is no more than a couple person-days, "medium" is no more than a couple person-weeks, "large" is no more than
by SketchySeaBeast 8y ago
> Everything gets a T-shirt size. Roughly, "small" is no more than a couple person-days, "medium" is no more than a couple person-weeks, "large" is no more than a couple person-months.
That's pretty much exactly what I've ended up using on past projects - a little more fine grained (start at a half day, went up to months), but that was my approach as well, and if I didn't know everything it went up a size.
- karthikb 8y agoDid you find much differentiation between half day and couple of days? Especially because some things that might take a couple days end up taking 30 mins (some efficient package already exists), and some half day things end up taking a couple days, so it comes out in a wash?
- SketchySeaBeast 8y agoHalf day items were strictly bound, well know problem, like a label change, or a piece of functionality I knew by heart to be that size. I found that those items usually helps balance out the larger item misses.
- bunderbunder 8y agoThe answer to that question depends heavily on the duration and nature of your planning iterations. If you're doing quarterly planning, the difference between half a day and a couple a days is meaningless, and there's not really any point in distinguishing among them. If you're doing 1-week sprints, the difference between half a day and a couple days is enormous, and the product planner might get some value out of distinguishing among them. If you're following a more kanban-y approach, the difference is perhaps meaningful, but not particularly actionable, so I think I (personally) still wouldn't bother to capture the distinction for planning purposes.