The biggest problem is that engineers tend to think in man-hours and managers think in calendar time. If I say a project will take 2 days, it'll probably take
by Consultant32452 8y ago
The biggest problem is that engineers tend to think in man-hours and managers think in calendar time. If I say a project will take 2 days, it'll probably take 2 days, but it might span 4 calendar days because other things are going on.
The biggest thing that has helped me here is to keep a running list of my tasks, an informal Gantt chart, and show it to the manager whenever they ask me about an estimate. This helps me communicate in a way they understand.
- Bartweiss 8y agoThere's a lot of bad to be said about how companies use story points and velocity and all the rest, but I do greatly appreciate the way they delink "amount of work" from "delivery date". It's a nice built-in way of expressing time requirements separately from schedule, which is a lot smoother than constantly reminding people that the difference exists.