besides the inherent difficulty of estimating the resources required to finish a large project that hasn't been done before... i think what willie brown descri
by arthur_pryor 8y ago
besides the inherent difficulty of estimating the resources required to finish a large project that hasn't been done before...
i think what willie brown describes here is also part of the problem providing estimates for the time required to complete software projects: if we gave more honest answers as devs, bosses and people signing contracts would blanche, so instead of standing firm, we go lower, or cut corners, or both.
i think the two things compounded together (inherent difficulty of estimating large unique projects, aversion to seeing real costs) are why estimates so often skew too low when we're trying to predict how long it will take to write a thing.
- watwut 8y agoIn fixed priced contracts, that strategy makes employer loose money. Some projects truly should be be starter, because their price is indeed too high compared to benefits.
- arthur_pryor 8y agoyeah, and i'm absolutely not trying to justify this outcome, just trying to think out loud about the unsatisfactory state of things.