One perspective is that negotiation of schedule and resources is often nothing resembling estimation but is a political game. Ed Yourdon's book "Death March" ha
by shoo 8y ago
One perspective is that negotiation of schedule and resources is often nothing resembling estimation but is a political game. Ed Yourdon's book "Death March" has a chapter about Negotiation .
http://ptgmedia.pearsoncmg.com/images/013143635X/samplechapter/013143635X_ch03.pdf http://ptgmedia.pearsoncmg.com/images/013143635X/samplechapt...
There's a list of "negotiation games" that, sadly, you'll probably recognise. And a bit of more practical advice:
>> The problem I have with “estimate” is that I understand
>> the word to mean, “best assessment knowing what is known
>> at this moment and what can reasonably be predicted about
>> the future.” From experience, what I have seen happen is
>> that once an estimate is published,it becomes a rock
>> solid commitment representing the maximum amount of
>> resources needed to accomplish the project phase or the
>> entire project.
> Unfortunately, there’s an uglier aspect of the political
> negotiation when you introduce the plus-or-minus
> qualifier into your estimate: You’ll be accused of
> uncertainty, wishy-washiness, weakness, or even
> incompetence. [...] What senior management really wants
> is a firm commitment — a promise that the project will
> be finished on a certain deadline, with a budget of a
> certain number of dollars, and a staff of a certain size.
> This gives them the enormous luxury of (a) no longer
> having to worry about the problem for the duration of the
> project and (b) having a convenient scapegoat to blame if
> the promise is broken.
> Jim McCarthy, in his excellent book, Dynamics of Software
> Development, suggests that the project manager needs to
> confront this head-on and persuade the customers and/or
> senior management that they need to share some of the
> burden of uncertainty [around schedule, cost, resourcing]
> that the entire project team will be living with on a
> day-to-day basis. Thus, the project manager effectively
> says to the customer or the senior management group,
> “Look, I don’t know precisely when this project will
> finish — but since I’m the project manager, I’m far more
> likely than anyone else in the organization to figure it
> out as soon as it can be figured out. I promise you that
> once I know, I’ll tell you right away.”
> Only a manager with a lot of self-confidence, and the
> ability to walk away from the assignment, has the
> chutzpah to say something like this in the politically
> charged atmosphere of a death march project. The time to
> say it is at the beginning of the project; after all, if
> the customer and senior management do not respect your
> ability as a project manager, and if they don’t realize
> that you do have a better chance of knowing when the
> project will finish than anyone else, then why are they
> putting you in charge of the project in the first place?
> Are you being set up as a scapegoat? Are you going to
> be a “puppet manager,” with all the decisions being
> made by other political manipulators in the
> organization? If so, now is the time to get out!
> Similarly, if you’re a lowly programmer on the project
> team and you see political games like this, it may be a
> strong indication that your project manager (a) doesn’t
> have the confidence to believe in any estimate that he
> puts forth, (b) doesn’t have the backbone to stand up
> for himself and for the project team, and/or (c) has
> gotten himself into a political situation where all the
> key decisions will be made by people who are not
> directly involved in the project. Again, this is a
> strong indication that the project is doomed; and
> before you get too deeply involved, it might be a
> better idea to seek greener pastures.
Refusing to be pressured into emitting on-the-spot "estimates" that will be regarded as commitments is a useful life skill. Teach your new hires: http://www.dadhacker.com/blog/?p=2267 http://www.dadhacker.com/blog/?p=2267
- jcadam 8y agoBah, your estimate is meaningless anyway, since someone five levels above you in the org chart has already promised the customer that feature X would be available in 3 weeks. And that promise was made last Tuesday, so by the time it gets to you, there are only two weeks remaining until the deadline. You'll know this is the case when you say "at least a month", and the PM looks at you like you just shot his dog. "The answer I need is two weeks."
- mekane8 8y agoI found Steve McConnell's (of Code Complete) breakdown of estimates, targets, and commitments super helpful: https://www.youtube.com/watch?v=FY9X21HA02w https://www.youtube.com/watch?v=FY9X21HA02w