3 ms·
Companies, and often just about any type of business, will often seek to convert variable costs into fixed costs because they are more predictable and easier to
by ineedasername 8y ago
Companies, and often just about any type of business, will often seek to convert variable costs into fixed costs because they are more predictable and easier to plan for. It means they can project out over a given time frame and know what their costs will be. Variable costs are harder to plan for.
It's not unreasonable that they are seeking to make such a change. It is unreasonable if they expect your net income to decrease as a result. If you can, determine what your average weekly/monthly rate was over the past year, and then try to negotiate a fixed cost that is at least that much. Maybe a little more: you can argue the justification that you're giving up the possibility of making more should the % split fall that way. This could make it a win-win situation, where in effect you both get the benefit of stability in planning on fixed costs, and in your case fixed income.
Of course they may not be willing to negotiate, and then you need to decide if it's worth the possibility of lesser income, which of course depends on how easily you might find comparable work with comparable compensation.
- greenyoda 8y ago> Maybe a little more: you can argue the justification that you're giving up the possibility of making more should the % split fall that way. Another way to think of this is that the contractor would be personally taking on the risk of a cost overrun (which previously would have been borne by the customer, who would have had to pay more for additional hours of work). The amount they'd need to be paid for a fixed cost contract would need to take this risk into account. If I were doing contracting work, I don't think I'd ever take the risk of entering into a fixed cost contract for any non-trivial project, since I can't estimate programming work well enough to have any confidence that I won't end up doing the work at a loss.
- dugong 8y agoYeah, I'm guessing that the issue might be that they're trying/considering negotiating a flat rate(s) and/or monthly retainers, but I agree that it would be very difficult to do that profitably.
- ineedasername 8y agoAh, my interpretation was that the OP would be choosing between a % of the entire contract vs. a fixed hourly wage of some sort. A fixed price for the entire contract would indeed introduce complications of the sort you mentioned. And the one massive fixed price contract I've been involved with (on the client side, not the vendor, which was Oracle ::shudder::) went to sh#t when, despite the fixed-price contract, when there were cost over runs due to delays (roughly 20% blame on client, 80% on Oracle) the result was that Oracle took their ball and went home, virtually over night. A lawsuit ensued. (We won. We had a fixed price contract, they violated it)