Some of the French issue stems from wide-spread anti-nuclear sentiment. Fukushima galvanized a the anti-nuclear movement. Last month, Macron announced the clo
by mywittyname 8y ago
Some of the French issue stems from wide-spread anti-nuclear sentiment. Fukushima galvanized a the anti-nuclear movement. Last month, Macron announced the closure of Fessenheim plant after protests and petitions passed over fears of seismic activity and potential flooding.
- dv_dt 8y agoIf you set aside the public sentiment, the economic non-performance of Nuclear, despite investment, compared to other options is a bigger driver. https://www.bloomberg.com/news/articles/2018-12-10/french-power-costs-will-rise-if-renewables-are-sidestepped https://www.bloomberg.com/news/articles/2018-12-10/french-po... This conclusion from the same French agency has been the result since 2015, with prices of Renewable alternatives making that predicted result more and more solid.
- philipkglass 8y agoIf you look at the IAEA's Power Reactor Information System, French reactor builds took a long time even in the 1990s: https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.... The originally proposed construction schedule for Flamanville 3 was 4.5 years. That was a very aggressive schedule. Even reactors completed before Chernobyl, e.g. Cruas 3, took more than 5 years: https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=200 https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.... The most modern operating French reactor, Civaux 2 (construction started 1991), took 11 years: https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=228 https://pris.iaea.org/PRIS/CountryStatistics/ReactorDetails.... Generation III reactors like the EPR and AP1000 were supposed to be simultaneously faster to build and safer due to standardization and careful design. The actual experience of building EPR and AP1000 reactors has torpedoed the "faster" part of that justification. The troubled, prolonged builds have also killed the original lower cost projections. At this point the the original cost and schedule estimates for EPR and AP1000 projects alike look so optimistic that they were basically fraudulent. These projects were troubled even before Fukushima aroused a new wave of anti-nuclear sentiment among the public. I still believe the empirical evidence that nuclear power is a very safe way to generate electricity. I also believe the empirical evidence that nuclear reactors are expensive and slow to construct. "Generation IV will be safer and faster to build" -- ok, for a while I believed those same claims about Generation III. The next time I'll believe those claims about a new reactor design is after it has already entered commercial service.