> But if measured by how many blocks and neighborhoods are absolutely finished,
> according to the urban planners’ artistic renditions,what is your progress?
> By that measure, your progress is zero.
Exactly! Do NOT create individual JIRA Task the size of each building/block. When planning a city, a JIRA Task is something like -
"Add switches to the bedroom of apartment 104 in the residential building at lot #10 on Sunshine street."
No wonder the author of this Techcrunch article is frustrated with JIRA. He is using JIRA wrong
(or more likely is being forced to use JIRA incorrectly)
One of the cardinal sins of project planning is to NOT decompose the activities into individual deterministic steps.
I have summarised my thoughts in this slide-deck that i find useful in my crusade against unplanned/misplanned projects
https://thecodeartist.blogspot.com/2017/04/effort-estimation.html https://thecodeartist.blogspot.com/2017/04/effort-estimation...