1. For estimates to become effective (in software) you need to estimate a lot of tasks' sizes/complexities and then record how long they took. 2. You need fami
by Jtsummers 8y ago
1. For estimates to become effective (in software) you need to estimate a lot of tasks' sizes/complexities and then record how long they took.
2. You need familiarity with the type of system you're working on (whether it's new development or sustainment doesn't matter, you need to know the system). If the work is new, you will need to work on it for a period of time to learn how to estimate it.
3. Initially, your estimated sizes and times will be way off. Accept this.
Record the estimated task size, record the final time taken (at least to the number of days needed). Run this through a stats package: You should see clusters, each size category should take around the same amount of time. If you see a size "small" or "1" taking as long as a "large" or "100", work on your size estimates.
Once you get better at estimating the size, you'll be able to (more easily) estimate the time (within some confidence interval).
I discourage estimating time directly ("Here's the task, I think it's 10 hours of work.") because you really don't know it. And everyone in my office that does the above and insists on estimating time (versus size/complexity) ends up using a multiplier against their time estimate after a couple years! That is, their time estimates become sizes after all. They keep calling it "100 hours" but then double it or halve it based on the statistical analysis above. Better to just call it a "10" and have the stats package spit out 200 hours or 50 hours or whatever is appropriate, eliminate the confusion.
============
For estimating longer term projects (not just tasks), you can do the above if you've worked with similar systems (or the system being maintained) for each of the tasks/features/bug fixes. String them together using a PERT chart (illustrating dependencies between these tasks and the path to your objective). This will give you a reasonable estimate for the overall project time.
============
Finally, because you're using stats and know your standard deviation, you don't give a precise target (100 hours). You give a range (100 hours +/- 10 hours). The more you (or your team) does the same kinds of work or work on the same systems, the tighter your bounds should become on your estimates.