Hmmm, with a cube 1x1x1 m I get: 35.315 cubic feet or 1.308 cubic yards or 1.000 cubic meters if pre-mixed concrete*, it is 4696.851 lbs or 2130.000 kgs if 6
by jaclaz 8y ago
Hmmm, with a cube 1x1x1 m I get:
35.315 cubic feet or 1.308 cubic yards or 1.000 cubic meters
if pre-mixed concrete*, it is 4696.851 lbs or 2130.000 kgs
if 60 lbs per bag, it is 78.281 bags
if 80 lbs per bag, it is 58.711 bags
The 2130 Kg/mc may be arbitrary, and, to be picky:
60x78.281x0,454= 2132,37444
still the (as well arbitrary) "adding 10% to allow for spillage and slab depth variations" seems like having been forgotten.