Yes and nuclear plants in the U.S. already pay for that, and it comes from the money paid by electricity customers.
by DennisP 8y ago
Yes and nuclear plants in the U.S. already pay for that, and it comes from the money paid by electricity customers.
- natmaka 8y agoUK: 15 reactors, ~10300 gross MWe. They analyzed and now think that decommissioning will cost £234 billion (309 billion USD). USA: 98 reactors, 100350 gross MWe. 46 billion USD (Nuclear Waste Fund) are in provision. One order of magnitude more power produced by the stuff to decommission, and nearly 7 times less money to do so. Decommissioning small and old reactors costs more, and ENTOMBing may, at least apparently (short-term), reduce the cost. In theory. Let's check a real and ongoing case: Oyster Creek. According to the EIA its construction costs were $488 million (2007 USD) ( https://www.eia.gov/nuclear/state/archive/2010/newjersey/ https://www.eia.gov/nuclear/state/archive/2010/newjersey/ ). As soon as the decommission project started the Nuclear Regulatory Commission announced that it will cost "about $1.4 billion to shut down the plant". Not for an immediate and complete decommission, because the plant will stay in a “safe store” condition until 2075, with dismantling ((...)) set for a period between 2075 and 2078 ( https://www.powermag.com/oldest-u-s-nuclear-plant-shuts-down/ https://www.powermag.com/oldest-u-s-nuclear-plant-shuts-down... ). Then new problems (costs!) may arise. Let's bet that, as usual, the taxpayer will pay.
- DennisP 8y agoThe trust funds for decommissioning are separate from the Nuclear Waste Fund.
- natmaka 8y agoGiven that * "Approximately 70 percent of licensees are authorized to accumulate decommissioning funds over the operating life of their plants." ( https://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html#funds https://www.nrc.gov/reading-rm/doc-collections/fact-sheets/d... ) * at least some plants will be closed ahead of schedule (it's already starting) => not enough accumulated funds * the effective decommission cost may be higher than planned (see the UK & Oyster cases) ... the Nuclear Waste Fund may prove useful as waste management is a non-neglectable part of a decommission. Will all the available funds be sufficient?
- dv_dt 8y agoThere is a nuclear plant decommissioning line item in my So Cal Edison bill that confirms that customers are paying, but invalidates that a sufficient amount was collected during the operating lifetime of the plant.