We had such a tech lead. He had never designed a system until this one. He used the very latest techniques and technologies. He estimated the contract and recom
by daly 8y ago
We had such a tech lead. He had never designed a system until this one. He used the very latest techniques and technologies. He estimated the contract and recommended a fixed cost 5 month contract with 5 people. The project was terminated after 18 months with 10 people full time. All 27 developers from the company were fired and within a year the company went under.
- UK-Al05 8y agoIf a company can go bust just because a lead developer gave a bad estimate(not uncommon) there is something else deeply wrong at that company.