This is a good advice and all three points are spot on (on time deliveries are unusual; management likely knows you are late; messengers often get shot). You d
by ptero 8y ago
This is a good advice and all three points are spot on (on time deliveries are unusual; management likely knows you are late; messengers often get shot).
You do need to figure out for yourself a realistic, pretty safe time when you will be ready: an extra month? three months? never? You say the work is outside your team's comfort zone. This is potentially a much bigger red flag than being late. Will the team learn and deliver, or it just cannot execute at the speed requirements are changing or will soon be? Be brutally honest with yourself.
If you think you can safely deliver the product in, say, three extra months, then keep working but be ready with good estimates when the time comes to redo the schedule. When that discussion comes (usually suddenly), having a clear plan and realistic estimates that you can confidently present will likely give you (most of) what you ask for. IME really bad options are either agreeing to fix everything in a week (if you know it will take three months) or not having an estimate at all "we are burning midnight oil and I cannot tell you when we will be done". Either could lead to quick problems.
IME when "what do we do with this crap" time comes, senior management does not care why you are late (everyone is at least some of the time). They want to know if you have a plan and look ready to execute it. Just my 2c. Good luck!
- scubaguy 8y agoGreat answer