This is literally what agile is for. Step 1 (and this is the hardest part) is to negotiate the need for either a flexible scope or deadline. Accept that you're
by tootie 8y ago
This is literally what agile is for. Step 1 (and this is the hardest part) is to negotiate the need for either a flexible scope or deadline. Accept that you're estimate for a fixed scope will just never be accurate and just make room to adjust. Putting "buffer" into your estimate is also not the right approach because it's planning for failure. Flexible scope means you have work to fill up what would go into your buffer that you can launch without if you need to, but would be very nice to have.
Create your high-level backlog and do MoSCoW prioritization. Figure out your "musts", "shoulds", "coulds", "wonts". Now apply some estimates to your features and add 10% for unforeseen growth. Estimate velocity based on team size and now you've got a date when you could conceivably hit your musts, shoulds, coulds. Set your "deadline" if you must somewhere deep in the coulds. If your musts go over, you are still able to launch an MVP. If things go well, you can start delivering non-musts.
Adjust your plan every sprint based on actual velocity.