E = (a + 4m + b) / 6 where a = the best-case estimate m = the most likely estimate b = the worst-case estimate That's my favorite, called Three-point Estimat
by jonheller 9y ago
E = (a + 4m + b) / 6
where
a = the best-case estimate
m = the most likely estimate
b = the worst-case estimate
That's my favorite, called Three-point Estimation: https://en.wikipedia.org/wiki/Three-point_estimation https://en.wikipedia.org/wiki/Three-point_estimation