I worked with a project manager who loved large long status meetings and requirements meetings. It was getting to the point nothing was getting done. Most of the people in the meeting were contractors. 8 people at $100 bill rate was $800 each meeting. I had to put a stop to it. I started a virtual status meeting. I opened a slack channel at 10:00 and everyone posted their updates. If the PM wanted to know anything else they would have to go to the individual dev.
Anyone was free to leave the slack channel after they posted their update.
I told them unless the meeting request was coming from me or someone higher up in my management change, that all meeting requests were just that "requests" that they were free to decline if necessary.