Thanks and interesting. If you have written up your full system anywhere I would be interested to read more.
by markphip 9y ago
Thanks and interesting. If you have written up your full system anywhere I would be interested to read more.
- lliamander 9y agoIn terms of mapping story points to time ranges, here's the full list: 1 point -> 2-4 hours 2 points -> 4-8 hours (1 day or less) 3 points -> 1-2 days 5 points -> 3-5 days (up to one week) 8 points -> 5-9 days (up to one two-week sprint[0]) 13 points -> 2-3 weeks (1-1.5 sprints) 20 points -> 3-4 weeks (up to two sprints) 40 points -> 1-2 months Anything beyond 40 needs to be aggressively analyzed broken down into steps, even if those steps are not deliverable features per se. [0]For a two-week sprint, you have to account for at least one day each sprint for demos, retrospective, and planning. Thus, you have at most 9 days for implementation and testing. EDIT: Fixed formatting.