> Second, if story points are not an indirect measure of time, then why are you pointing stories? What does the pointing gain your team other than fluff? The p
by jack9 9y ago
> Second, if story points are not an indirect measure of time, then why are you pointing stories? What does the pointing gain your team other than fluff?
The points can (and should) be assigned before the work arrives. Agile planning is a little more nuanced. There's business valuation (points from business development) which then become stories that are estimated during/over another sprint. The points don't correlate directly to hours because you haven't assigned points or know what resources will be on the estimated sprint. That is the responsibility of the Scrum master to handle. If people are vacationing, sick, replaced or there are new hires, you put a variable time-value on the points. Most importantly, you put a few stories in the current sprint off the top of the queue and pull as time allows. Telling the engineers that "all these stories must be done by the end of the sprint" negates the whole process.
> Finally, I have not seen, and you have not presented, evidence that engineers are good at estimating.
In general, nobody else is capable of coming close. That being said, I've blown up estimates to maximum by inquiring about specific details (what file, function, library, what repo, do you have creds for that, how long are the code reviews, etc) in a majority of tasks because some engineers are good as estimation for specific implementations, otherwise they concede on identified complexity/meta-process. Small, Medium, Large seems like the correct approach.