I once worked in an organization that only allowed engineers to make estimates once, at the beginning of typically 6 month projects. No elaborate research was a
by valuearb 9y ago
I once worked in an organization that only allowed engineers to make estimates once, at the beginning of typically 6 month projects. No elaborate research was allowed, all estimates were given off the cuff in a single 1 hour team planning session.
In the 6 years I was there they shipped around 40 different software products, without once shipping late or a buggy product, and won dozens of industry awards.
It's not time estimations. Its how you manage your process.
- sumedh 9y ago> 40 different software products What kind of software products?
- valuearb 9y agoGraphics and desktop publishing utilities. And I mistyped, it wasn't 40 different products, it was 40 different major releases, only about 8 different products. Though hundreds of minor releases counting Japanese, Spanish, French and German versions, and point releases.